Quote Contingency: Cost the Uncertainty and Explain the Scope
A quote contingency is a planning allowance for identified uncertainty in your cost estimate. List the risks, estimate their possible cost and choose how to handle each before adding an allowance. Keep it separate from profit and from any contractual process for variations. An internal contingency does not give you a right to charge extra later.
What you’ll get from this guide: Create a risk register and a traceable contingency allowance for a particular quote.
- Investigate uncertainty before paying for it through a larger allowance.
- Label probabilities and ranges as estimates supported by the available evidence.
- Keep the cost model separate from the customer agreement.
This worksheet suits a service owner quoting a job where quantities, site access or supplier availability are uncertain. It helps explain the estimate. It does not provide contract clauses or decide whether a later charge can be recovered.
Start with a base estimate that can be explained
List the ordinary quantities, internal cost rates and supplier prices. Remove any hidden general buffer before adding a separate contingency. If labour already includes two hours for difficult access, don't add the same access risk again.
Write the assumptions you could resolve before quoting. A site visit, measurement or current supplier quote may remove uncertainty more cheaply than a large contingency. Keep the evidence date so an old quote isn't mistaken for a current commitment.
Build a small risk register
Assumptions: Fictional Australian-dollar management-costing example. Amounts exclude GST that is assumed recoverable; any non-recoverable tax is already included in costs. These assumptions do not establish your GST entitlement. Contribution is before unallocated overheads and income tax.
| Uncertainty | Illustrative extra cost range | Assumed chance | Weighted allowance | Evidence and treatment |
|---|---|---|---|---|
| Difficult access | $0–$400 | 25% | $100 | Access photos incomplete; inspect first |
| Supplier substitution | $0–$120 | 50% | $60 | Availability unconfirmed; obtain a valid quote |
| Extra material quantity | $0–$250 | 20% | $50 | Measurement incomplete; verify dimensions |
| Total allowance | All three high costs: $770 | Judgement inputs | $210 | Review after the missing evidence arrives |
Original ASBG worked example. All businesses, amounts and scenarios are fictional. The table contains the same figures as the visual.
Here each risk is simplified to two outcomes: no extra cost, or the full listed extra cost. Multiplying cost by the assumed probability gives $100, $60 and $50. The resulting $210 is an expected-cost allowance across those assumptions, not a maximum loss and not a guarantee that $210 will be enough for this job.
If all three high outcomes occurred, extra cost would be $770 within this limited model. Other risks could exist outside it. For this particular job, check whether you could also fund the larger scenario.
Keep cost, contingency and price separate
Assumptions: Fictional Australian-dollar management-costing example. Amounts exclude GST that is assumed recoverable; any non-recoverable tax is already included in costs. These assumptions do not establish your GST entitlement. Contribution is before unallocated overheads and income tax.
| Line | Without contingency | With modelled contingency |
|---|---|---|
| Base delivery cost | $3,000 | $3,000 |
| Identified uncertainty allowance | $0 | $210 |
| Planning cost | $3,000 | $3,210 |
| Price at a chosen 25% margin | $4,000 | $4,280 |
Original ASBG worked example. All businesses, amounts and scenarios are fictional. The table contains the same figures as the visual.
The second price is $3,210 ÷ 0.75 = $4,280, before the model's assumed GST. The 25% is a chosen margin for the example, not an industry target. Adding 25% to cost would be a markup and would produce a different margin.
The $210 cost allowance and the margin solve different problems. One addresses estimated delivery uncertainty; the other is the gap between revenue and modelled cost. Keep the margin separate when checking how much uncertainty the estimate allows for.
Choose a treatment for each risk
You might inspect the site and remove the uncertainty, obtain a supplier commitment, narrow the scope, include an allowance in a fixed price, or propose a clearly documented variation process. The right choice depends on the work and the agreement.
If access remains unknown, write what access the estimate assumes and how a change would be handled. Don't leave the scope vague and expect the customer to fund the difference. Have the actual quote and variation terms reviewed where enforceability or consumer obligations are in question. Business.gov.au's quote guide is a useful starting checklist for that discussion.
Update the register after the job
Record which risks occurred, the actual extra cost and whether the estimate missed something else. A contingency that is never used may reflect cautious estimates; one that is exceeded repeatedly may reflect poor scope information. Compare like jobs before changing the assumptions.
The budget-versus-actual method helps keep that review connected to evidence. Keep the original estimate as well as the updated version, so you can see what was known at the time of the quote.
Where to get help
Use the completed-job review for actual results and rush-job costing for a deadline that disrupts capacity. Revisit pricing strategy and the pricing and profit hub for the wider decision.
Where to go from here
Job Profitability Review: Compare Your Quote with Actual Costs
Find the estimating assumption to change after a job.
3 min readAllocate Overheads to Jobs: Choose a Cost Driver That Fits
Check which shared costs the work needs to recover.
3 min readRetainer Profitability: Measure the Work Behind the Monthly Fee
Continue the “cost a job” reading sequence.
3 min read
General information only. This guide doesn't take your personal or business circumstances into account and isn't financial, legal or tax advice. Rates and thresholds change — check the official sources linked in this guide and get qualified advice where your circumstances require it.